by David Porter | Sep 12, 2025
Attention: Vendors and Subcontractors The anticipated construction schedule was issued this morning showing this project about 5 months out from beginning, so pleased updated your pricing accordingly. This project is rebidding 3/31/2026 due to the fact that the...
by David Porter | Aug 18, 2025
Attention: Addendum 01 has changed the bid date to 9/4/25.
by David Porter | Jul 25, 2025
by David Porter | Jul 9, 2025
Attention: Permit drawings were just issued for this project that previously bid last year. RFI Log just issued does have the DDC system in the core & shell bid tomorrow.
by David Porter | Jul 8, 2025
Attention: Addendum 06 only changed the bid form. Addendum 01 was just the revised drawings set. Addendum 05 added an air compressor to the Plumbing scope and an additional exhaust fan to the Mechanical scope.